There Are 5 Matters Needing Attention To Take Over Outside Cross Flow Cooling Tower
Dec 08, 2018

1. The pipes on both sides of the cooling tower should be of the same length as far as possible to ensure the balance of resistance;

2. Valves shall be installed in every inlet and outlet pipe of the cooling tower to adjust the water quantity;

3. Pipe design should be as simple and direct as possible;

4. Welding operation on the tower is prohibited. Construction shall be carried out far away from the tower body during welding.